The Heart of Bay View Campaign

for John M. Hall Auditorium

Tentative Project Costs

SOUND AND ACOUSTICS $580,000
Sound System Replacement  
Install Hearing Assistance System  
Relocate Sounds Booth to Main Floor  
Technical Upgrades to Organ Console  
   
LIGHTING AND ELECTRICAL $350,000
Upgrade Audio/Visual Controls  
Upgrade Recording Capacity  
Lighting Instrument Upgrades  
Lighting Location Upgrades  
Relocate Lighting Controls to Main Floor Booth  
   
SAFETY AND CODE $220,000
Electric Wiring Replacement  
Protection Upgrade for Electrical Equipment  
Balcony Railing Revisions  
Accessibility Requirements  
   
AMENITIES, COMFORT AND USABILITY $350,000
Remove Blinds and Replace System of Light Control  
Partial Replacement of Main Floor Seating  
Replace First Two Rows of Balcony Seating  
Provide Exhaust Above Stage  

New Restroom Facilities for Performers/Participants
(This portion of the project, completed in 2010, was funded by a major gift to the Heart of Bay View Campaign by anonymous donor.)

 
   
TOTAL PROJECT $1,500,000
Related costs included in the above are
Escalation, Contingencies, General Conditions, Fundraising Fee, Architectural/Engineering Fees, Printing, Permits
 

Follow these links for more information on the Heart of Bay View Campaign for John M. Hall Auditorium:

Heart of Bay View Campaign

Introduction

The Case for Support

Confessions of a Perfectionist

Campaign Cabinet

Gift Acknowledgement Levels


Heart of Bay View Flyer (pdf)

Contribute


This page last updated Friday, July 09, 2010 4:24 PM.
Copyright © 2010 by Bay View Association of the United Methodist Church, PO Box 583, Petoskey, Michigan 49770. All rights reserved. SiteMap
Powered by SiteChalk